The village property 1-3 Main Street is currently the site of a proposed project for the Adirondack Park Agency (APA) Headquarters. As project information becomes available it will be shared on the webpages linked below: 

The Village of Saranac Lake and the Adirondack Park Agency are working together to advance the new APA headquarters at 1–3 Main Street. This page addresses common questions about the project, lease, public access, parking, utilities, and long-term responsibilities.

What does the project include?
The project includes rehabilitation of the existing buildings, construction of a new three-story headquarters building, utility improvements, parking, accessible walkways, landscaping, and stormwater controls.

Who owns the property?
The Village owns the property and will continue to own it. APA will own the improvements during the lease term, with ownership transferring to the Village when the lease ends.

Does the Village own the Pelkey Lane property?
Yes. The Village owns the Pelkey Lane property. It is included in the APA lease and will remain permeable for snow storage.

Why is the rent $1 per year?
The State is making a substantial investment in the property, including construction and rehabilitation. APA will also pay for its separately metered utility use, and the improvements will ultimately transfer to the Village.

Will APA receive the Village’s hydroelectric credits?
No. The Village retains its hydroelectric credits.

How much parking is proposed?
The plan provides 60 parking spaces, including four accessible spaces. APA uses the lot during weekday business hours, 5:00 a.m. to 5:00 p.m. Village and public use is during evening, weekend, and holiday periods.

Will the Riverwalk and waterfront remain open?
The Riverwalk, park, shoreline, and canoe access remain outside APA’s leased premises and available to the public. The project includes sidewalks, crosswalks, and accessible connections toward the waterfront.

What public amenities will be available in the APA headquarters?
APA is providing community meeting space and restrooms for public use. Access will be managed according to APA’s building hours and use policies.

Who will remove snow?
APA is responsible for parking-lot maintenance and snow removal during its weekday operating hours. The Village is responsible during the evening and weekend public-use periods.

Who is responsible for building maintenance?
APA is responsible for its improvements, leased areas, and routine roof maintenance. The Village remains responsible for structural building elements, surrounding landscaping, and public infrastructure.

Will the sanitary sewer be relocated?
Yes. The existing Village sewer main must be relocated to avoid the new building. The relocation is included in the OGS project plans and requires Village approval and inspection.

What happens to existing water lines?
Existing utilities must be located and verified before construction. The contractor must protect them and repair any project-related damage. No confirmed conflict requiring relocation of the reservoir water line has been documented.

How will stormwater be managed?
The project includes a cascade separator, infiltration areas, stormwater planters, drainage improvements, and erosion controls. APA is identified as the construction-phase stormwater operator, and its project team must complete required inspections, records, corrective work, stabilization, and permit closeout.

How will construction affect other Village projects?
OGS is coordinating the APA headquarters design and construction. Physical work will be coordinated with the Village’s utility, Riverwalk, and waterfront projects through the respective engineers and project managers.

Boothe River Park remains a separate regulatory project because APA is reviewing the Village’s application for that project.

Will the project increase Village insurance costs?
The Village already insures the property. The Village’s insurance agent does not currently anticipate a significant immediate increase. Final costs will depend on the construction insurance arrangements and the completed property value.

What could the property cost the Village in the future?
In 2025, the Village spent $20,607 on the property. Using a reasonable 6% annual planning increase for inflation and a vacant, aging building, that cost could reach approximately $27,600 annually within five years and $36,900 annually within ten years. The cumulative ten-year cost would be approximately $288,000, before major elevator, structural, roof, or mechanical repairs.

What approvals are required?
The project is proceeding through the Village’s development review process, including SEQRA review, area variances, and site plan review. The area variances concern building setbacks, parking location, and retaining-wall height.

Who is funding the APA headquarters project?
This is a State-funded headquarters project for a State regulatory agency. Village property taxes are not paying for the project’s design or construction.

Are the Village and APA working together?
Yes. The Village and APA have signed the lease and are working together to deliver the best possible project for the community. The partnership brings substantial State investment to Village-owned property, provides public amenities, and transfers the completed improvements to the Village at the end of the lease.